The Town measures construction time limits from the original building permit issuance, and later permits for the same project do not add time. The ordinance does not say whether a sale resets that clock.
The Town Council adopted the current version of these rules on second reading on October 21, 2026. The construction time limits moved into a new Municipal Code Chapter 15.41, and an updated Construction Management and Operations Plan, or CMOP, ordinance was adopted alongside them, according to the City Manager's recap of that meeting. Staff described the time-limit move as a reorganization with no change to the substantive requirements. The CMOP piece is newer, and it expressly carries its obligations through a change of ownership. The time-limit chapter does not address a sale either way.
Construction time limits
Chapter 15.41 covers any building construction that needs a permit, including additions, alterations, substantial remodels, repairs and demolition. The limit depends on project size:
| Project size in the ordinance table | Time limit, counted from original permit issuance |
|---|---|
| 2,000 square feet or less | 12 months |
| 2,001 to 4,000 square feet | 24 months |
| Larger projects | 36 months |
The finish line is defined strictly. Construction counts as complete only after the Town's final inspection and approval, once the work is done, permit conditions are met, and construction materials and debris are cleared from the site. Landscaping has its own separate deadlines.
A 2023 Town handout distinguishes permit validity from the construction time limit.
What the days past the deadline cost
After the deadline passes, the ordinance allows 30 days without a penalty. Daily penalties start after that and get steeper.
- Days 31 through 60: $200 per day, up to $6,000 for that stretch
- Days 61 through 120: $400 per day, up to $24,000 for that stretch
- Day 121 onward: $1,000 per day, with no cap stated in the adopted text
The Town also asks for cash or security. When the deadline arrives and the project has no final inspection or certificate of occupancy, the owner must post a $30,000 deposit or a qualifying bond. By day 120 the required deposit rises to $220,000. If either deposit is missing, the Building Official issues a stop-work order.
The ordinance also addresses circumstances beyond an owner's control and appeals.
The Town has held this line for years. In September 2019, The Almanac reported that staff had granted one extension since the three-year limit took effect in 2006, that 13 projects had gone past the deadline since 2015, and that deposits totaled $538,800. Town staff and the Council saw uncapped penalties as a reason to finish, since construction nuisance lasts until a project is done. The following month, The Almanac reported that the Council had removed the earlier $250,000 penalty cap.
What changes hands at closing
The October ordinances answer some questions about a sale directly. Others they leave to the documents.
The CMOP ordinance says the approved CMOP and CMOP Agreement are binding conditions of the building permit until the Town finalizes it. It also says a change in property ownership, contractor or other responsible party does not end the project's obligation to comply. The Building Official may require a successor owner, developer or contractor to acknowledge the CMOP before work continues.
The CMOP agreement template addresses notice to a purchaser before a transfer, sale or conveyance.
Chapter 15.41 does not say whether a sale resets the time limit, and it does not spell out a successor owner's liability. The chapter also addresses unpaid penalties and liens. Whether a sale changes the deadline, and who answers for penalties that accrued before closing, are questions for the Building Department and the parties' attorneys.
This leaves a few figures for each side to establish early:
- The original permit issuance date and the time limit that applies to it.
- The work left before final inspection, including debris removal and open conditions.
- Whether any deposit has been posted, or any penalty has started to accrue.
- A realistic completion date.
The answers feed into price. A seller whose project still has a year on the clock is offering a different asset from one whose deadline falls a week after closing, even if the framing, finishes and square footage match.
The work-hour rules sit on top of the clock
Completion time also depends on how many hours crews can actually work, and the October update tightened those hours. The amended Chapter 15.40 generally prohibits construction, construction-related activity, pickups and deliveries from 5 p.m. to 8 a.m. on weekdays, and all day on Saturdays, Sundays and listed Town holidays. Under the CMOP form, workers may not arrive, park, wait or gather at or near the site before 7:30 a.m. Off-hours work needs a discretionary exemption permit obtained in advance, and planned exemption work requires notice to properties within 300 feet. Weekend catch-up shifts are not an easy option.
Parking and staging follow the same approach. On-site parking comes first, any approved street parking is limited to the site's own frontage on the same side of the street, delivery vehicles may not stage or queue on public streets, and debris in the adjacent right-of-way must be cleared by the end of each workday. The Town's September 30 monthly report says about 50 builders and residents attended the builders' roundtable on these changes, and that enforcement could include citations, fines and stop-work orders. The ordinance recitals cite "multiple ongoing and projected large-scale construction projects" as the reason for the update.
One more requirement affects final inspection. Atherton keeps a 75% construction and demolition debris diversion requirement, above the 65% CALGreen minimum. Under amendments introduced October 21, refundable deposits will give way to registering the project in Green Halo, a tracking system, as a condition of the building permit, with compliance shown there before final inspection. Staff are targeting a January 1, 2027 launch, with full enforcement starting then and education-focused enforcement through the end of 2026. A separate Green Halo fee was still to come before the Council. Existing deposits on active projects will still be tracked, and eligible refunds will be processed as those projects finish.
The 36-month tier
Where does the exact square-footage cutoff fall for the 36-month tier? The 2026 ordinance text and the 2023 Town handout word the top tier slightly differently, so confirm the exact threshold for a specific permit with the Atherton Building Department.
This is general information about Town rules, not legal, tax or financial advice. Confirm how these rules apply to your property with the Atherton Building Department and your own attorney before you sign.
If you are weighing whether to finish a project before listing, or what an open permit means for a home you are considering, Adela Gildo-Mazzon can help you work out the remaining timeline and coordinate the finish work with the contractors and inspections it depends on. Request a Confidential Home Valuation to start with a number that accounts for the permit history.